Five Points Roundabout Traffic Improvement Works

Five Points Roundabout Traffic Improvement Works

The latest phase of work at Five Points Roundabout and its approach roads will begin in September 2025 on behalf of Buckinghamshire Council.

The project will include enlarging the roundabout to improve traffic flow, upgrading footpaths and traffic islands, installing new signage and signals, pedestrian crossings and road resurfacing. These improvements are designed to make journeys safer and smoother for everyone using the area, whether by car, bicycle, or on foot.

The works will take place in stages:

  • Ground investigations from Monday 15 September 2025 for approximately five weeks.
  • Main construction works will follow, starting Monday 17 November 2025, continuing until March 2027.

Traffic management measures will be in place throughout the work. Some overnight closures (8pm–6am) will be necessary towards the end of the works; these will always be communicated to local residents, businesses and road users in advance.

Every effort will be made to keep disruption to a minimum. Access for residents and businesses along Uxbridge Road, Pinewood Road, Church Road, Slough Road, and Wood Lane will be maintained at all times. The team is committed to ensuring residents can reach their homes and premises with minimal impact.

Updates will also be posted on the Buckinghamshire Council designated website

www.buckinghamshire.gov.uk/five-points-iver

If you have any questions the designated Project Manager is Darryl Allen and he is reachable on 07824 665 247 email: darryl.allen@erith.com